What is claimed is:
1. A method for installing an offshore pipeline, comprising:
structurally connecting an inner pipe and an outer at a terminal end of a pipe-in-pipe flowline having an annulus between the inner and outer pipes;
placing centralizers in the annulus to prevent buckling of the inner pipe which takes lateral support from the outer pipe;
suspending the working end of the pipeline under construction in a substantially vertical position within slips at the weld floor of a J-lay installation barge;
adding a section of inner pipe, comprising:
grasping a section of inner pipe, orienting the section of inner pipe to a vertical position;
bringing the section of inner pipe into abutting position with the inner pipe at the working end of the pipeline under construction;
welding the section of inner pipe to the inner pipe of the working end of the pipeline under construction; and
coating the inner pipe with an arc resistant material;
adding a section of outer pipe, comprising:
grasping a section of outer pipe, orienting the section of outer pipe to a vertical orientation;
sliding a section of the outer pipe down over the section of inner pipe just welded to the working end of the pipeline under construction;
bringing the section of outer pipe into abutting position with the working end of the pipeline under construction; and
welding the section of outer pipe to the outer pipe of the working end of the pipeline under construction presented through the slips at the weld floor of the installation barge;
advancing the end of the working end of the pipeline through the slips to bring the end of the section of outer pipe added adjacent the weld floor; and
repeating the foregoing steps to add additional sections of inner and outer pipe as necessary to complete the pipeline.
2. A method for installing an offshore pipeline in accordance with claim 1 wherein grasping a section of inner pipe comprises connecting an internal plug within an end of the section of inner pipe.
3. A method for installing an offshore pipeline in accordance with claim 2 wherein grasping a section of outer pipe comprises engaging a collar / elevator about a shoulder presented on an end of the section of outer pipe.
4. A method for installing an offshore pipeline in accordance with claim 3 wherein the sections of inner and outer pipe are grasped concentrically and brought into position over the working end of the pipeline under construction.
5. A method for installing an offshore pipeline in accordance with claim 4 further, comprising taking steps to prevent water and debris from entering the annulus between the inner and outer pipes during construction.
6. A method for installing an offshore pipeline in accordance with claim 5 wherein coating the weld at the inner pipe with an arc resistant material comprises sealing the weld with a shrink sleeve.
7. A method for installing an offshore pipeline in accordance with claim 6, further comprising installing insulated panels over the shrink sleeve.
8. A method for installing an offshore pipeline in accordance with claim 7, wherein the insulated panels between the two welds comprise a high temperature thermal insulation material.
9. A method for installing an offshore pipeline in accordance with claim 1, further comprising providing a corrosion coating over the outside of the weld joining the section of outer pipe to the outer pipe of the working end of the pipeline.
Other References
"Cable-Free Electrical Systems for the Oil to Gas Industry," Production Technologies Company, L.L.C., 600 Kenrick, Suite C-30; Houston, Texas 77060, advertisement, Copyright 1996, 6 pp.
"Dunbar in Depth," Offshore Engineer, Dec. 1994, 2 pp.
"Monolithic Pipeline Electrical Isolation Joints," HydroTech Systems, Inc., Engineered Pipeline Products, advertisement, Nov. 1996, 6 pp.
"Skin Effect Pipe Heating Systems," Thermo Systems Technology, Inc. (TST), Four Commerce Park Square, 23200 Chagrin Boulevard, Suite 600, Beachwood, Ohio 44122, Copyright 1991, advertisement, 4 pp.
B. J. Eastlund et al., "New System Stops Paraffin Buildup," Petroleum Engineer, Jan. 1989, 3 pp.
Monobloc Insulating Joints Type "IK".
Stop Paraffin Build-up and Realize Your Well's Full Potential . . . Plug in Paratrol. International, Inc. (PTI), 15423 Vantage Parkway East, Houston, Texas 77032, advertisement, Copyright 1989, 6 pp.
A. Anselmi et al., "TTDPIS: A New Underwater Technology in the Field of Traced Insulated Pipelines," 1994 OMAE, vol. 5, Pipeline Technology, ASME, 1994, pp. 69-76.
"Taking Induction Heating Underwater," Process Heating, Jul./Aug. 1995, 1 p.
"Tubing Casing Wireless Telemetry (Tucas System)," Schlumberger web page (1993?/Jun. 1996), 16 pp. (See text of Supplemental Information Disclosure Statement re supposed date of technology described.).
Brochure--Combi Pipe--the end of clogged pipelines, Alcatel Contracting Norway and Aker Engineering, 7 pp. (Undated. See text of Supplemental Information Disclosure Statement re supposed date of technology described.).
Anecdote--Fuel Oil Between Buildings (See text of Supplemental Information Disclosure Statement.).
Anecdote--Asphalt Transfer Liner from Tank Cars et al. (See text of Supplemental Information Disclosure Statement.).
Anecdote--Thermo Systems under river crossings. (See text of Supplemental Information Disclosure Statement.).
H. Collins and M.A.R. Lyle, "Progress Reported in Design of Reelable Insulated Subsea Flow Lines," Oil and Gas Journal, Sep. 24, 1990, pp. 102-106.
Krevelen, D. W., Univ. of Technology, Delft, The Netherlands, "Properties of Polymers", 3rd Edition (Revised). Elsevier: Amsterdam-Oxford-New York-Tokyo, 1990: pp. 641-653.
Gaylord, N. G., Gaylord Associates. Newark, New Jersey, "Polyethers--Part I. Polyalkylene Oxides and Other Polyethers": Interscience Publishers: New York-London-Sydney, pp. 9-80.
Brochure--Why Use Skin Effect Pipe Heating? Thermo Systems Technology, Inc. Four Commerce Park Square, 23200 Chagrin Boulevard, Suite 600, Beachwood, Ohio 44122, Copyright 1991, 2 pp.
F. Aarseth and E. Bentsen, "Heating of Pipelines, and Power Supply to Subsea Electrical Equipment,"Aker Engineering a.s A. Bjømstad and B. Knutsen, Alcatel Contracting Norway a.s., DOT 1995, 23 pp.
Fred S. Epstein and Gary L. White, "Understanding Impedance Heating," Chemical Engineering, May 1996, p. 112-118.
Brochure--World Wide Experience List--Compressed Gas Insulated Transmission Bus System Type CGIT, ABB Power T & D Company Inc., 30 Oak Street, Westborough, MA 01581, USA, 6 pp. (Describes work from 1972. Dated Oct. 1996. See text of Supplemental Information Disclosure Statement re supposed date of technology described.).
Compressed Gas Insulated Transmission Bus Ducts, ABB Power T&D Company, CGIT/IPB Division, Westborough, MA USA, 22 pp. (Undated. Describes work from 1972. See text of Supplemental Information Disclosure Statement re supposed date of technology described.).
Brochure--New Double Pipe Insulated System (DPIS) Designed by Snamprogetti, Snamprogetti Offshore Division, 6 pp.
"Introduction to Direct Heating of Subsea Pipelines," overview by Statoil, Saga Petroleum, CSO Norge, Alcatel, Kabel Norge and EFI, Feb. 1998. (Undated. See text of Supplemental Information Disclosure Statement re supposed date of technology described.).
N. B. Carson, "A New Method for Heat Tracing Long Pipelines," ASME, 74-Pet-35, paper presented at the Petroleum Mechanical Engineering Conference, Dallas, Texas, Sep. 15-18, 1974, pp. 24.
F. R. Newbold and T. K. Perkins, "Wellbore Transmission of Electrical Power", The Journal of Canadian Petroleum Technology, Jul.-Sep. 1978, Montreal, pp. 3-52.
K. H. Afkhampour, "A Novel Approach to Solving Downhole Fluid Flow Problems by Use of an Electric Heat- ing System," Paper No. PCIC-85-35, 12 pp.
R. Wash, "Electromagnetic Energy Helps Recovery," Gulf Coast Oil World., Jun. 1986, pp. 18-19.
F. G. Bosch, K. J. Schmitt, and B. J. Eastlund, "Evaluation of Downhole Electric Impedance Heating systems f Paraffin Control," Paper No. PCIC-90-34 presented at Industry Applications Society 37th Annual Petroleum and Chemical Industry Conference, Houston, Texas, Sep. 10-12, pp. 223-227.
M.I. Mollison, "Foam Insulation Gets First Reeled Installation off Australia," Oil and Gas Journal, May 18, 1992, pp. 80-82.
C. G. Langer, "Engineering Report--1979 Construction of the Cognac 12-inch Pipeline From Mississippi Cany Block 194 to Southwest Pass East Bay Central Facilities, Offshore Louisiana,"ES No. 74-82, Job No. 560513, Shell Oil Company, Pipeline Construction Department, *, 6 pp.
The Electrothermic Co. (TEC), 4916 Bear Lane, P. O. Box 4227, Corpus Christi, TX 78408 advertisement/sale brochure, 4 pp.
"New Double Pipe Insulated System (DPIS) Designed by Snamprogetti", Snamprogetti Offshore Division, Vial de Gasperi 16, San Donato Milanese, Milan, Italy, advertisement, 6 pp.
Protest Document, Dec. 8, 1987 letter of Andrew W. Marr, Jr. to the Assistant Commissioner of Patents requesting issuance of U.S. Patent 4,716,960, available in that file history as of Jan. 5, 1988. (with attachments, total of 12 pages).
"General Product Specification--Pipeline Insulating Joint," HydroTech Systems, Engineered Pipeline Products, advertisement, 7 pp
精准.石油.论坛 forum.petro-china.com
----
来源: 精准石油论坛 - 推进信息共享,提升科技水平